Rewiring a flat in 2026: cost, stages and testing

Rewiring a 50 mΒ² flat costs about 11–16k PLN, though some sites quote 4–5k. We explain the gap, when rewiring is necessary and what 5–10 working days with acceptance testing look like.

Redakcja RemontLab9 min read

Wiring is the renovation cost you never see but which decides safety. The spread of prices online can be startling, so first we explain why one site says 4 thousand and another 16.

Old electrical installation and a box in a block of flats
An old installation in a block – aluminium wires and no earthing are reasons to replace. Photo: Dmitry G, CC BY-SA 3.0, Wikimedia Commons.

When to replace

Replace if the installation is over 20 years old, dates from the 1970s–80s with aluminium conductors, has no earthing, too few circuits, or trips with several devices. If you cannot rewire everything, at least do the kitchen and bathroom.

When to replace the wiring
Fig. 1. Warning signs per muratordom.pl and kb.pl.

Cost

muratordom.pl (2026): sockets 90–130 PLN per point, lights 78–104, cable 26–52 PLN/m, board 312–780; a 50 mΒ² flat 11–16k PLN. kb.pl puts a turnkey point at about 170 PLN. Sites quoting 80–100 PLN/mΒ² (4–5k PLN) usually exclude chasing and fittings and assume fewer points. Always ask how many points are in the offer.

Unit prices of electrical installation items
Fig. 2. Rates from muratordom.pl (2026) and a price-list review; kb.pl's editors give about 170 PLN per point turnkey.

Stages: 5–10 working days

Marking out and removal 2–4 days, chasing and cables 1–2, boxes and board 3–5, making good 1–2, final fit 1, then testing. Cables go in before plastering; photograph walls before they are closed.

Stages of rewiring a flat
Fig. 3. Stages and time per cenauslug.pl; cables and boxes before plastering, final fit last.

Testing and formalities

Tests cover insulation resistance, loop impedance, continuity and RCDs (about 587–850 PLN for a flat). The report must be signed by a licensed person. Rewiring inside a flat usually needs no building permit; replacing the riser outside it needs the co-op's or community's consent.

Plan points per room with the electrical points calculator.

How many points in a flat – a sample design

The number of points drives the cost. For a 50 mΒ² flat (living room with kitchenette, bedroom, bathroom, hallway) assume roughly: living area 12–16 sockets and 3–4 light points, bedroom 6–8 sockets, bathroom 2–3, hallway 2, plus separate lines for hob, oven, dishwasher, washing machine and (if needed) air conditioning. That gives 50–70 points. muratordom.pl's per-point prices (socket 90–130 PLN, light 78–104) and kb.pl's average (about 170 PLN per turnkey point) give 6–12k PLN for the points alone, to which the consumer unit, main cables and tests are added – 11–16k PLN together. This is our own calculation on assumptions, not source data.

The consumer unit – what it should contain

  • Main switch and an overcurrent breaker for each circuit.
  • 30 mA residual-current devices (RCDs) – protect against shock, at least one per group of circuits.
  • Surge protection (SPD) – 270–620 PLN per cenauslug.pl; protects electronics.
  • Spare space – a few free modules for future circuits.

cenauslug.pl prices fitting a board up to 24 modules at 580–850 PLN and above 24 modules at 850–1,350 PLN; material (a 72-module board about 380 PLN, an RCD about 180 PLN) is a separate line.

Kitchen and bathroom circuits – practical rules

  1. Induction hob, oven and dishwasher get their own lines, not a shared socket circuit.
  2. In a bathroom sockets are supplied through an RCD; avoid sockets directly next to the shower.
  3. Washing machine and dryer – separate circuits, preferably outside the bathroom or respecting the zones.
  4. Split lighting into circuits so one fault does not black out the whole flat.

What you can do yourself and what needs a licence

Replacing fittings (sockets, switches) with the power off is a job for a competent person, but running new cables, fitting the board and acceptance tests are done by a licensed electrician. Per cenauslug.pl only a test report signed by a licensed person has legal force and is sometimes required by an insurer; unreported work on an installation can result in a refused claim.

Rewiring in a block – extra issues

  • The riser and its cable (the supply to your flat) – replacing it outside the flat needs the co-op's or community's consent.
  • Switching to three-phase – an application to the grid operator; it usually takes 30–60 working days.
  • Noise and dust – agree working hours with neighbours and the administrator (see our guide on renovating in a block).

What to check afterwards

  1. The test report (insulation resistance, loop impedance, earth continuity, RCD tests) stamped by a licensed person.
  2. A labelled consumer unit – every circuit named.
  3. An as-built diagram or photos of cables before plastering.
  4. A guarantee on the work.

Plan points in the electrical points calculator and add the result to your shopping list.

Where the sites disagree

SiteWhat it saysNote
muratordom.pl11–16k PLN for 50 mΒ²; cable 26–52 PLN/m; prices rose 10–15% in 2026Explains the signs of an old installation
kb.plAbout 170 PLN per point on average; circuit rules (≀20 light points, ≀10 sockets, ≀3.5 kW)Wiring schemes
cenauslug.plStages of 5–10 days; tests and acceptance; the board and mistakes in choosing itA licensed electrician must sign the report
pewnylokal.plReplace when the installation is over 20 years oldThe source offers services

Checklist before rewiring

  1. Commission a design of points and circuits.
  2. Fix the number of sockets and lights in each room.
  3. Hire a licensed electrician and ask for the test report.
  4. Photograph walls before plastering.
  5. Check whether a block needs consent for work on risers.
  6. Keep the diagram and the report.

Frequently asked questions

How long does rewiring take?

Usually 5–10 working days for a 50 mΒ² flat.

How many electrical points in a 50 mΒ² flat?

Usually 50–70 (sockets, lights, separate lines). That is our assumption – the exact number depends on equipment.

Can I replace sockets myself?

Replacing fittings with the power off is possible, but new cables, the board and acceptance tests are done by a licensed electrician.

Sources and real examples

The figures in this guide come from the pages below (accessed at publication). Prices change – check current quotes.

  1. muratordom.pl – rewiring cost 2026
  2. cenauslug.pl – rewiring a flat: stages and formalities
  3. cenauslug.pl – measurements and acceptance

Redakcja RemontLab

The desk collects prices, checks formulas and cites every number.