Materials and quantities3 min read
new tool
Renovation planner – schedule
Plan the order and length of work: demolition, installations, plaster, screed, tiling, floors and painting. A chart that allows for drying and crew size.
Draws a Gantt chart with drying breaks for plaster and screed
How this calculator works
For every stage, duration is a fixed part plus a part that depends on size, scaled to crew size (base 2 people). Stages follow the typical order, and after plaster and screed we add drying time.
The result is a range (−15% / +30%) because real renovations always slip.
Calculator results and prices are estimates only. Check the manufacturer's data sheet before buying materials and ask a contractor for a quote.
Frequently asked questions
How long does a 50 m² renovation take?
A full renovation with installations is usually 2–4 months, a simple refresh 2–4 weeks.
Why does screed lengthen a renovation?
It must dry before tiles and floors – usually a 3–7 week pause.