Screed drying time calculator

See how long cement, anhydrite and self-levelling screeds take to dry and when you can lay tiles and flooring or switch on underfloor heating.

Turns screed thickness into dates for the next jobs

Enter the details

cm

Self-levelling: usually 0.3–1 cm.

How this calculator works

For cement and anhydrite screeds we assume about 7 days per cm up to 4 cm and about 14 days per additional cm before tiling. Before wood and panels we add 20–50%.

Self-levelling screeds dry much faster, but the time depends on the product.

Calculator results and prices are estimates only. Check the manufacturer's data sheet before buying materials and ask a contractor for a quote.

Frequently asked questions

How long before tiling on screed?

For a 6 cm cement screed about 8 weeks (4 cm × 7 days + 2 cm × 14 days = 56 days).

When to switch on underfloor heating?

Usually after 21–28 days, following a heat-up programme: gradually, a few °C per day.

Also count