Planning
The right order of renovation work: where to start
The wrong order doubles your costs. Here is a proven plan: demolition, installations, plaster, floors, paint and fitting.
Redakcja RemontLab6 min read
On this page
The costliest renovation mistakes are not the wrong tiles but the wrong order: a painted wall that must soon be chased, or a new floor flooded by screed. This is a map of what comes after what, and why.
- Plan and formalities – layout, key materials, any permits or building-management consent.
- Demolition – old floors, tiles, wallpaper, partition walls; arrange rubble removal.
- Installations – electrics, plumbing, heating, ventilation, while walls are open. Photograph pipe and cable routes.
- Windows and entrance door.
- Plaster, screed and skim coat – give screed time to dry and check moisture before laying floors.
- Bathroom and tiling – waterproofing, tiles, grout, then sanitaryware.
- Floors.
- Painting – primer plus two coats; protect the new floor.
- Fitting – interior doors, sockets, lighting, kitchen, wardrobes, skirting, final clean.
Rule of thumb: wet and dirty jobs first, clean and delicate jobs last.

How long it takes in practice
Guides quote 3–4 weeks for a bathroom alone (5–6 with plumbing changes); a whole flat grows with size, crew and drying breaks. Use the renovation planner for a timeline chart and the screed drying calculator for tile and flooring dates.
Why the order matters
Sources differ in detail but agree on the pattern: demolition → rebuild → installations and screed → finishing. Start with painting and then chase cable channels and you paint twice. Lay the floor before plaster and skim coats and dust and water ruin it. kb.pl and pewnylokal.pl show this logic in their planning guides, and some add a practical tip: renovate the hallway last, because materials and crews pass through it and it is easiest to clean then.
How long it takes – what the sources say
There is no single answer. According to the guides we compared, a minimal flat renovation is about a month, and a general renovation of a flat in poor condition can take up to half a year. Pace depends on the crew, availability of materials and sticking to the schedule. Made-to-measure furniture is a separate wait: roughly 2–5 weeks (kb.pl), so order it when measurements after plastering are ready rather than at the end. Add a reserve to quotes and dates: guides recommend 15–20% of the budget for unforeseen costs and a detailed schedule attached to the contract.
Sample schedule: a 50 m² flat, general renovation
| Week | Stage | Notes |
|---|---|---|
| 0 | Plan, design, orders, co-op consent if needed | Order kitchen furniture and windows early |
| 1 | Demolition, tile removal, rubble removal | Skip, protect the stairwell |
| 2–3 | Installations: electrics, plumbing, heating | Photograph installations before plastering |
| 3–4 | Windows, plaster, screed | Screed dries for weeks |
| 5–6 | Skim coats, sanding, primer | The dustiest work |
| 6–7 | Bathroom and kitchen: tiles, fittings | Waterproofing before tiling |
| 7–8 | Floors, doors, skirting | Floors after skim coats, before the last paint |
| 8–9 | Painting, furniture fitting, lighting | Final clean |
This is our own sample schedule, not source data – every crew and flat has its own rhythm. Screed drying and furniture lead times can stretch the whole by several weeks.
Dependencies – what must come before what
- Electrics and plumbing before plaster – chases must be cut and closed before walls are levelled.
- Windows before plaster and skim – replacing windows after plastering ruins the reveals.
- Screed before skim coats – and underfloor heating pipes go in before the screed.
- Bathroom tiling before floors elsewhere – water and mortar will not harm wood or panels.
- Painting, then skirting, then touch-ups – so you do not paint over the skirting.
Staged payments
pewnylokal.pl's guide to settling with a crew advises splitting payments into stages tied to acceptance of parts of the work instead of paying everything up front. Keep any advance small – our budget and contract guide explains why an advance above 30% is a red flag.
Common planning mistakes
- No detailed schedule in the crew contract.
- Ordering made-to-measure furniture before plaster and screed are done.
- Planning screed and tiling without drying time.
- Ignoring seasonality: crews can be booked half a year ahead.
- No space for storing materials and protecting common areas.
Build your own schedule in the renovation planner.
How long a renovation takes, per other sites
| Site | What it says | Note |
|---|---|---|
| kb.pl | Rules for planning stages; a minimal renovation about a month, a general one up to half a year; made-to-measure furniture 2–5 weeks | Time depends on the flat's condition and the crew |
| pewnylokal.pl | Schedule: demolition → rebuild → installations and screed → finishing; hallway last | Staged payments |
| muratordom.pl | Schedule and cost of work in a house renovation; reserve 15–20% | Attach the schedule to the contract |
Checklist before starting
- Write down the scope and order of work.
- Order windows and made-to-measure furniture early.
- Book the crew and sign a contract with a schedule.
- Arrange a skip and storage for materials.
- Agree hours and consents with the administration.
- Leave a time reserve for screed drying.
Frequently asked questions
Paint or floors first?
Usually floors first, then paint, with the new floor protected.
Where do I start a flat renovation?
With a plan and demolition: remove old finishes, then do installations and screed, and finishing last.
How long does a general flat renovation take?
At minimum about a month, up to half a year if the flat is in poor condition – much depends on the crew and materials.
Sources and real examples
The figures in this guide come from the pages below (accessed at publication). Prices change – check current quotes.
Redakcja RemontLab
The desk collects prices, checks formulas and cites every number.
Did you like this guide?
Get the next ones once a month.